Field Connection Point (FCP), also known as Cross-Connect Collocation, is a demarcation point outside of the Qwest Central Office (CO) where your facilities interconnect with Qwest facilities. The FCP is located in the Feeder Distribution Interface (FDI) /Serving Area Interface (SAI) or other accessible terminal (e.g., a Controlled Environmental Vault (CEV), cabinet or pedestal). The FCP provides a point of interconnection away from the Qwest CO and provides access to the following sub-loop elements:
The placement of cable facilities within Qwest's FDI/SAI for the sole purpose of creating a cross-connect field to support sub-loop unbundling constitutes a FCP. A cross-connect field is created when a Competitive Local Exchange Carrier's (CLEC's) cable is tied down to a termination block that is owned by Qwest.
The FCP is similar in function to an Interconnection Distribution Frame (ICDF) Collocation in the CO environment, but is located in the field. You will not have physical access to the splice points at Qwest's accessible terminal (e.g., FDI/SAI), however if you wish to request a non-standard access arrangement you can utilize the Special Request SR Process.
Product Diagram
FCP is available where facilities exist throughout Qwest's 14-state local service territory where technically feasible and there is an accessible terminal.
Terms and conditions are included in your Interconnection Agreement; if these terms differ from those set forth in this web page, then the terms of your Interconnection Agreement may prevail.
A FCP can be established within a Qwest accessible terminal (e.g., FDI/SAI). If space within the accessible terminal is legitimately exhausted, the FCP may be placed in an adjacent terminal, when technically feasible.
If the FCP consists of a separate cabinet that is placed by Qwest, Qwest will allow more than one CLEC to share the FCP for purposes of interconnecting with Qwest at the FDI or at other technically feasible points.
The FCP must be established prior to ordering Sub-Loop UDL and Sub-Loop UFL and Shared Distribution Loop. If you require UFL, you will need a CO Collocation and a FCP. For access to the UDL and Shared Distribution Loop, CO Collocation is not required.
You are required to obtain the Access to Poles, Ducts and Rights of Way (ROW), all necessary permits and approvals, and perform the necessary trenching required to bring your cable to the Qwest accessible terminal (e.g., FDI/SAI). You are also required to leave enough slack in the cable so Qwest can splice the cable into the Qwest accessible terminal (e.g., FDI/SAI).
In Colorado only, you may reserve sub-loop elements prior to completion of the FCP; refer to the Colorado Sub-Loop Reservation Process for more information.
Remote Terminal / Feeder Distribution Interface Move with CLEC Presence
The Move RT/FDI with CLEC Presence is a Qwest initiated procedure established for moving and or relocating a Qwest remote premise or a feeder distribution interface.
If a requirement identifies that a remote terminal or feeder distribution interface should be moved or relocated, i.e. roadway expansion, each CLEC with a presence in the premise will be notified by email of the impending relocation activity.
The Collocation Project Management Center (CPMC) will contact each CLEC to schedule a coordination call. During this call, CPMC will inform the CLEC of any options they may have involving the premise move, establishment of a timeline, and review the design job. While attending this call, you are expected to identify the methodology by which you will affect the transfer of equipment and/or services to the new location. For example, you will be required to indicate whether you will duplicate your equipment at the new site or do an "Out Of Service" cutover utilizing the existing equipment. A site survey, consisting of a coordinated review of potential work, is scheduled during this meeting. The site survey occurs within a few days from the coordination call.
The CLEC is expected to notify Collocation Project Management Center, (CPMC) State Project Manager via Email sent to rfsmet@qwest.com of its finalized methodology choice within 10 calendar days after the site visit. If the notification is not received within 10 calendar days from the site visit, Qwest will move forward with the methodology indicated during the coordination call.
Remote Terminal and Feeder Distribution Interface relocations may require CLLI changes, which will require changes to account records. Updating account records will be handled as a project within the overall premise relocation project.
All relocation projects and the responsibility of charges for each sites relocation will be handled on an individual case basis, (ICB).
When the project is complete Qwest will send out a notification via email and coordinate a site acceptance walk-through.
Nonrecurring charges are comprised of the following rate elements:
Quote Preparation Fee (QPF)
You will be charged a Quote and Preparation Fee (QPF) for the work to determine if the FCP request is feasible at the requested location.
You will be charged a nonrecurring charge consistent with Exhibit A of your Interconnection Agreement. The one-time nonrecurring charge will be developed on an Individual Case Basis (ICB) and consists of the costs to establish or augment the FCP. If the accessible terminal needs to be expanded to accommodate your request, the cost will be passed on to you as part of the nonrecurring charge.
Wholesale rates for this product or service, including tariff references and any applicable discounts, are provided in your current Interconnection, Resale, Commercial or other governing agreement.
Tariffs, regulations and policies are located in the state specific Tariffs/Catalogs/Price Lists.
There are no optional features associated with this product.
| Features | Benefits |
| Interconnection to Qwest Network at any technically feasible point. | You gain the ability to access and pay for only the sub-loop elements you require. |
You may use a FCP to access sub-loop elements at any technically feasible point as follows:
You want to interconnect with Qwest to provide Digital Subscriber Line (DSL) service to a Multi-tenant Dwelling Unit/Campus environment. When you check the loops of certain end-users using a Raw Loop Data Tool, you discover that none of the loops qualify because of distance and Pair Gain. You then decide to apply for FCP to avoid the Pair Gain and reduce the loop length.
The diagram below depicts access at the accessible terminal:
If you are a new CLEC and are ready to do business with Qwest, view Getting Started as a Facility-Based CLEC. If you are an existing CLEC wishing to amend your Interconnection Agreement or New Customer Questionnaire, additional information is located in the Interconnection Agreement.
If terms and conditions for FCP are not included in your Interconnection Agreement, you will be required to amend your Interconnection Agreement. For additional information, refer to Getting Started as a Facility-Based CLEC or contact your Qwest Sales Executive.
It is recommended that you use one of the Qwest Loop Qualification tools to obtain facility information and determine whether facilities exist and are compatible with the service you want to provide. The facility information is dynamic. Facilities may be available at the time you perform the query and may not be available when you place the order. For additional information on Qwest's Loop Qualification Tools, refer to Pre-Ordering section of Unbundled Local Loop - General Information or the Pre-Ordering section of Shared Distribution Loop.
Prior to ordering FCP, you can request a Distribution Area (DA) Map at the Wire Center Level. You can utilize this map to determine which DAs serve a particular area. The DA Map also contains the DA number that is needed on the order form. Application and APOT(s) forms specific to Field Connection Point (FCP)/Cross-Connect Collocation can be found under Applications and APOT forms table in the Collocation - General Information. Return the completed order form to rfsmet@qwest.com and copy your Wholesale Collocation Project Manager.
In Colorado only, you may reserve sub-loops if they are available; the reservation takes place at the time you submit a request for a FCP. Refer to the Colorado Sub-Loop Reservation Process for more information.
To initiate the FCP ordering process, the FCP Request Application form, including detailed map or diagram must be complete and accurate before it will be accepted as a valid application. Application and APOT(s) forms specific to Field Connection Point (FCP)/Cross-Connect Collocation can be found under Applications and APOT forms table in the Collocation - General Information.
Information on how to cancel a Field Connection Point (FCP)/Cross-Connect Collocation order already in progress is located in the Collocation - Cancellation Overview process. Collocation application forms can be found under Applications and APOT forms table in the Collocation - General Information.
Information on how to decommission a completed Field Connection Point (FCP)/Cross-Connect Collocation site is in the Collocation - Decommissioning Overview process. Collocation application forms can be found under Applications and APOT forms table in the Collocation - General Information.
Once you have submitted a complete and accurate FCP Request Application, the ordering process described in the Ordering section of Collocation - General Information will apply.
If you want to make changes to your order after you have submitted the application to Qwest, review the Major/Minor Matrix in the Collocation-General Information to obtain the effect on the interval. For specific information regarding time frames for the Feasibility, Quote and Acceptance stages detailed in the Ordering section of the Collocation - General Information, refer to your Interconnection Agreement.
If you require additional terminations after the establishment of the FCP, submit an FCP Request Application requesting an augment following the ordering process detailed in the Ordering section of Collocation - General Information.
After you have established your FCP and have received Alternate Point of Termination (APOT), you can reclassify your spare terminations. Refer to the Field Connection Point - Reclassification Process. For more information about the APOT form, refer to the Provisioning and Installation section of this web page.
For Colorado only, refer to the Colorado Sub-Loop Reservation Process , for the process to reserve sub-loop elements prior to completion of the FCP.
Early Ordering - For information on how to proceed with your FCP order once an agreement is executed, but prior to Commission approval, refer to the Opportunity for Early Ordering section of Getting Started as a Facility-Based CLEC.
Service interval guidelines and are found in the Service Interval Guide (SIG).
Once you have accepted the quote and upon receipt of the 50% payment, Qwest will begin the engineering, space design, procurement of materials, conditioning of space and the installation of your FCP request.
You are required to obtain ROW and perform all of the necessary trenching required to bring your cable to the Qwest FDI/SAI.
You are responsible for constructing the cable facility up to the Qwest FCP location. You are required to have your cable in place and ready for splicing 21 calendar days before the Request For Service (RFS) date. If it is not in place, the FCP request will be placed on CLEC Hold. The maximum time for a CLEC Hold is 60 calendar days. On the 61st day, the FCP request will be cancelled, and you will be charged all applicable fees beyond the 50% payment.
You may inquire as to the status of your FCP request at any time by contacting the CSIE. If there is a delay that will impact your RFS date, Qwest will notify you, via a telephone call or email, with the reason for the delay, the corrective action being taken and the anticipated impact on your RFS date.
The APOT identifies the specific terminations at the FCP and will be used for the purposes of ordering Unbundled Network Elements (UNEs). You will receive two emailed APOTs, a Preliminary APOT and a Final APOT.
Upon completion of the FCP order, you and the State Interconnect Manager (SICM) will jointly conduct the Acceptance Walkthrough of the work. Any exceptions will be documented and the SICM will forward them to the CPMC for resolution. In addition, the SICM will answer any questions you might have.
If you are unable or elect not to participate in the Walkthough within 21 calendar days from the scheduled RFS date, the SICM will facilitate a Walkthough and sign the FCP Acceptance form noting that you did not participate. If you do not participate in the Walkthough and have questions about activities associated with the Walkthough, contact your Qwest Wholesale Collocation Project Manager.
General maintenance and repair activities are described in the Maintenance and Repair Overview.
You can access the FCP for maintenance and repair purposes by contacting the Account Maintenance Support Center (AMSC) at 1-800-223-7881.
Billing and Receivable Tracking (BART) billing is described in Billing Information - Billing and Receivable Tracking (BART).
Local Qwest 101 "Doing Business With Qwest"
Collocation
View additional Qwest courses in the Course Catalog.
Qwest contact information is located in Wholesale Customer Contacts.
1. Can a CLEC use the FCP to access a Multi-Dwelling Unit
(apartment complex)?
Yes, if there is an accessible terminal on the property to access
the distribution cable. If you require access to the Intra-Building
Cable, a Multi-Tenant
Environment (MTE)-Point of Interconnection (POI) is required.
2. Must the FCP be constructed using a separate structure?
No, in most cases, space is available in an existing access terminal;
however, if space does not exist a separate structure may be used
or constructed.
3. Can the FCP be used to deliver High Speed Data services
to end-users?
Yes, Qwest is not concerned with the type of equipment that you
place at your equipment location as long as it does not interfere
with the services already being provided to end-users. Remember
the FCP is solely for the purpose of cross-connecting your cable
facilities with Qwest cable facilities and does not provide space,
power or heat disbursement for the placement of equipment. If you
wish to place equipment at a Qwest site refer to the Remote
Collocation web page.
Last Update: May 1, 2009
NC/NCI is a Trademark of Telcordia Technologies, Inc.